SDG&E sold 16,164,015 MWh of electricity during 2013.
SDG&E procured 3,811,607 MWh of renewable energy during 2013.
Out of 3,811,607 MWh of renewable energy, solar PV accounts for 791,675. This means that solar represents 20.7% of the renewable procurement.
It is still 20.7%, but it was a big jump from 2012. During 2012, only 3,264 MWh of solar was procured.
Some of utility-scale solar projects contributed to SDG&E's achievements in 2013 were:
- Cataline Solar Project (143 MW-DC/110 MW-AC) in Kern County
- CSolar South Solar Project in Imperial County
- Campo Verde Solar Project(139 MW-AC) in Imperial County
- Arlington Valley Solar Energy Project (127 MW-AC) in Arlington, AZ
CSolar South project in the Imperial Valley |
More solar projects are expected to be connected and deliver electricity this year. In 2014, the total procurement of solar is supposed to increase to 2,021,699 MWh - 2.5 times of 2013, according to the plan submitted to the CPUC.